 EX-GRATIA AMOUNT IN CASE OF NON-DEPARTMENTAL FATAL ACCIDENTS

PROCEDURE FOR CLAIMING DEATH COMPENSATION DUE TO ELECTRIC SHOCK

 

 

------------------------------------------------------------------------------------------

Service Standards of APNPDCL

APNPDCL is aware that consumers desire better service rendered to and it has plans to improve the level of service with technical excellence. The resource constraint and the unprecedented load growth are coming in the way. As a strategy, the Government of A.P. has restructured the organization to attract resource inputs for taking up System Improvement works like erection of sub- stations, lines, additional transformers etc. The standards and bench marks set to improve services include maximum time or response to important aspects of service.

A summary of the time limits for rendering service to consumers in LT/HT categories are as follows:

 
Sno
Type of Service
Time limit for rendering the service
1 Low Voltage
  local problems 10 days
augmentation of distribution 120 days
erection of 33/11 KV substations 1 year
2 Restoration following Interruption/Failure of Power Supply

(a) Fuse Off Calls
Cities & Towns 2 to 6 working hrs
Rural areas 12 Hrs
(b) Street Lights
Rectification of line fault 24Hrs
Replacement of fuse or defective lamp in twin cities 7days
(c) Breakdowns
Rectification in Cities 2 to 6 Hrs
Rural areas 24 Hrs
(d) Replacement of failed Distribution Trs.
Cities & Towns 24Hrs
Rural areas 48 hrs
e) Replacement of damaged service wires
7 days
3 Pre-planned Interruptions in supply
Will be informed through Press to public at 24 hrs beforehand.
4 Metering problems
  (a) Meter Replacement
Burnt Meters 7 days
Stuck up Meters 15 days
(b)Shifting Meter Lines/Poles  
Dismantling charges at the old site Same time schedule as that of release of new connection
Transportation charges from the old site to the new site
Re-erection charges for the new site
Depreciation on old materials if any not used at new site
Overhead charges on cost of new materials if required
Cost of irretrievable materials
5 Billing errors and Accounting
  Wrong billing 15 days
Finalization of back billing 30 days
Finalization of theft or malpractice 90 days
Disposal of appeal 90 days
6 Disconnection and Reconnection of Power Supply
  LT Consumers To pay within 14 days from receipt of bill Reconnection within 15 days of receipt of complaint after payment of dues
HT Consumer To pay within 15 days from receipt of bill Reconnection within 15 days of receipt of complaint after payment of dues
7 Disputed Bills
 